Building a Custom Home in Toronto, Step by Step
A custom home in Toronto passes through the City several times before and during construction: a zoning review, sometimes the Committee of Adjustment, building and demolition permits, site notices and inspections. This page sets out each stage, what the City asks for, and who handles it.
Building a custom home in Toronto: who does what at each stage
As of November 2026.
Swipe the table sideways to see all columns.
| Stage | What happens | The City's part | Who handles it with Khales |
|---|---|---|---|
| 1. Lot and zoning review | What the zoning and the site allow | Zoning by-law, tree and heritage rules | Khales reviews; the owner decides |
| 2. Design | Architecture and interiors, with the budget | None yet | Khales designs with the owner |
| 3. Zoning Applicable Law Certificate | The City checks the plans against zoning and applicable law | Toronto Building | Khales prepares and manages the application |
| 4. Committee of Adjustment (if needed) | Minor variances for anything past the zoning limits | Committee of Adjustment hearing | Khales manages the application and coordination |
| 5. Building, demolition and tree permits | Permits to build the new house and take down the old one | Toronto Building; the City's tree permit process | Khales manages the applications; some forms are the owner's |
| 6. Construction | Notices, building, inspections | Site notices and inspections | Khales runs the site |
Before design: what to check on a Toronto custom home lot
The first question is what the lot allows. Khales reviews the zoning, setbacks, lot coverage, height and grading before design starts.
Three City rules are worth checking at the same time:
- The zoning by-law. City-wide Zoning By-law 569-2013 sets the limits for each zone, and some lots are still also subject to a former municipal by-law.
- Trees. As of November 2026, private trees with a trunk diameter of 30 cm or more, measured 1.4 m above the ground, are protected, and removing or injuring one needs a permit. Lots in ravine areas fall under the Ravine and Natural Feature Protection By-law.
- Heritage. Some properties are listed or designated on the City's Heritage Register. Work on a designated property needs a heritage permit before it starts.
Designing the custom home: drawings and budget together
Architecture and interiors are developed by one team with construction input, and the budget is developed alongside the drawings rather than after them. The design stays inside the limits found in stage 1 unless there is a reason to ask for a variance, and that decision is made here, before the plans go to the City.
Custom home permits in Toronto start with a Zoning Applicable Law Certificate
As of November 2026, a Zoning Applicable Law Certificate is a detailed review by Toronto Building that confirms a proposal complies with the zoning by-law and other applicable law. It replaced the City’s earlier Preliminary Project Review in March 2022.
For a new detached or semi-detached house, Toronto Building treats a building permit application without an issued certificate as incomplete. In practice, the certificate is the step that turns the design into a complete permit application.
When a custom home needs the Committee of Adjustment
If the design goes past a zoning limit, such as height, depth or a setback, the owner applies to the Committee of Adjustment for a minor variance. As of November 2026, the process runs like this:
Before applying. A zoning review with Toronto Building is recommended, so every variance the design needs is identified.
Application and notice. The City circulates the application and notifies neighbours of the hearing.
Public hearing. The Committee, a quasi-judicial body of citizen members appointed by City Council, hears the application. Hearings run in a hybrid format, in person and online, and neighbours can make written or spoken submissions.
Decision. The Committee can approve, approve with conditions, or refuse.
Appeal period. The applicant and certain other parties can appeal to the Toronto Local Appeal Body within the appeal period. If no one appeals, the decision becomes final and binding.
Then the permit. Once the decision is final, the building permit application goes ahead, and any conditions of approval are met.
Khales has experience with City of Toronto permits and the Committee of Adjustment, and manages the application and the coordination with the City.
The building permit and the demolition permit for a custom home
Building permit. Under the Building Code Act, a building permit is required to construct or demolish a building. Toronto Building reviews the application against the Ontario Building Code, the zoning by-law and applicable law.
Demolition permit. Where an existing house is coming down to make way for a new one, the demolition permit is applied for after the new house’s building permit application has been submitted. The owner signs an acknowledgement of the City’s demolition control conditions.
Tree permit. If construction would injure or remove a protected tree, a tree permit is needed as well.
On site: notices, inspections and building the custom home
Site notices. Under Toronto’s infill construction notice by-law, a residential demolition site posts a demolition notice before demolition starts, with one notice for each lot line facing a street. A construction site posts a construction notice when construction starts, and it stays up until an occupancy permit is issued.
Inspections. The permit holder notifies Toronto Building when each stage of work is ready for inspection.
Building. Demolition, excavation, structure, envelope, building systems and finishes, then custom millwork and landscaping, all run by one site lead with scheduled milestones and regular updates.
Building a custom home in Toronto: FAQs
Do I need a permit to demolish my house before building a new one?
Yes. As of November 2026, a demolition permit is required, and where a new house is replacing the old one, it is applied for after the new house’s building permit application has been submitted.
Is a Zoning Applicable Law Certificate required?
For a new detached or semi-detached house, Toronto Building treats a permit application without an issued certificate as incomplete, so in practice yes.
What happens if the Committee of Adjustment refuses a variance?
The applicant can appeal to the Toronto Local Appeal Body within the appeal period, or change the design so it no longer needs the variance.
Do I need a tree permit to build a new house?
Only if construction would injure or remove a protected tree. As of November 2026, that means a private tree with a trunk diameter of 30 cm or more, measured 1.4 m above the ground, or a tree covered by the ravine by-law.
Is building a house the same elsewhere in Ontario?
The Building Code Act and the Ontario Building Code apply across the province, so a building permit is needed everywhere. Zoning, variance hearings, tree by-laws and site notice rules are set by each municipality, so those steps differ outside Toronto.
Building a custom home in Toronto: related pages
Start building a custom home in Toronto with a lot review
Send us the address and what you want to build, and we’ll start with what the lot allows.
We use what you send only to answer your enquiry. See our privacy policy.